- 07:26 PM Task #14 (Blocked): Convince IT to get Jenkins on server
- Not hearing back from IT. Asked for status update.
- 07:25 PM Task #24 (In Progress): This is a backlog task check for the systems integration project
- 07:25 PM Task #24 (ToDo): This is a backlog task check for the systems integration project
- 07:23 PM Task #24 (In Progress): This is a backlog task check for the systems integration project
05/10/2023
- 06:53 PM Task #20 (Closed): Obtain ppt from Yash for test case archirtecture
- got it, all done.
- 06:40 PM Task #20 (Blocked): Obtain ppt from Yash for test case archirtecture
- Waiting on important information.
- 06:36 PM Task #20: Obtain ppt from Yash for test case archirtecture
- Adding a note here.
- 06:35 PM Task #20 (ToDo): Obtain ppt from Yash for test case archirtecture
- 06:17 PM Task #20 (New): Obtain ppt from Yash for test case archirtecture
- Assigned to Brad
- 05:26 PM Task #20 (Closed): Obtain ppt from Yash for test case archirtecture
- 06:50 PM Task #22 (Rejected): Check on IT for team proposal about approving the server build.
- 06:47 PM Task #22 (ToDo): Check on IT for team proposal about approving the server build.
- 06:46 PM Task #22 (Rejected): Check on IT for team proposal about approving the server build.
- 06:38 PM Task #17 (ToDo): Create a software to update the firmware on BMS
- Re-assigning to brad
- 06:37 PM Task #17 (In Progress): Create a software to update the firmware on BMS
- 06:35 PM Task #17 (ToDo): Create a software to update the firmware on BMS
- Assignment to Bill
- 05:26 PM Task #17 (ToDo): Create a software to update the firmware on BMS
- 06:37 PM Task #14 (In Progress): Convince IT to get Jenkins on server
- 06:35 PM Task #14 (ToDo): Convince IT to get Jenkins on server
- 06:18 PM Task #14 (New): Convince IT to get Jenkins on server
- Assigned to george for new sprint.
- 05:25 PM Task #14 (Blocked): Convince IT to get Jenkins on server
- We want it, go get it.